EETC to do more studies for monorail
The Egyptian Electricity Transmission Company (EETC) will finish studying the electric feeding system of the monorail project linking the New Administrative Capital (NAC) to 6th of October city by September.
A source close to the project told Daily News Egypt that the operation of the monorail will need 140 MW.
He added that four high-voltage stations (22/66 kv) will be established, and high-voltage cables will be laid with a total length of 89 km. Medium-voltage cables with a length of 100 km will also be used.
The source pointed out that a high-level delegation from EETC conducted several field visits to the site of the monorail lines to inspect the electricity system of the project. A detailed report is scheduled to be sent to the Minister of Electricity and the Minister of Transportation within weeks.